How to Open a Medical Center in Dubai and Get a DHA License

How to Open a Medical Center in Dubai and Get a DHA License

ZeroMax Group
· Updated

If you are working out how to open a medical center in Dubai, start with two things: who the regulator is and the order of the steps. The Dubai Health Authority (DHA) licenses health facilities, and inside Dubai Healthcare City the regulator is DHCA. The path looks like this: premises approved for medical use, a design by a DHA-prequalified consultant, initial DHA approval, a works permit plus Civil Defence and DEWA approvals, construction by a licensed contractor, the final DHA inspection and license activation. A 150-250 m² clinic in a ready unit usually gets through it in about 4-7 months; a new building takes years.

Who issues the license and the permits

First check which authority covers the location. DHA licenses every health facility in Dubai, free zones included, except Dubai Healthcare City. DHA approval is only part of the process, though: the works permit comes from the authority that controls the area where the building stands.

Where the center isWho licenses the medical activityWho issues the works permit
Mainland DubaiDHADubai Municipality
DDA areasDHADDA (fit-out permit or Building Modification)
Trakhees areas, such as Jebel Ali Free ZoneDHATrakhees CED
Dubai Healthcare CityDHCA RegulationsDHCA Engineering through the Masaar portal

DHA reviews its own scope only: the layout against the DHA Health Facility Guidelines (HFG) and the Dubai Universal Design Code. Fire safety under the UAE Fire and Life Safety Code and the Al Sa'fat green building rules are checked by Dubai Municipality and Dubai Civil Defence. If those bodies ask for design changes, the drawings have to go back to DHA, otherwise DHA may refuse to license the facility. That is why the design is prepared for DHA, DM and Civil Defence from day one, so nothing needs to be resubmitted after DHA approval.

How to open a medical center in Dubai in eight steps

The steps below follow the order almost every operator goes through when opening a center in leased premises. Some of them run in parallel, but none can be skipped.

1. Trade name and premises

You start with paperwork, not construction. Register the trade name with DET or a free zone authority and shortlist the premises. Plot zoning matters a lot here. In most residential zones (R1-R7 and RC1) a clinic is a conditional use and needs a separate approval from the Dubai Municipality planning department. In RC2 a clinic is permitted outright. For a hospital or a day surgery center, DM land use approval is obtained before the DHA submission. If an office or a shop is being turned into a clinic, that is a change of use of the premises, and in DDA areas it goes through as a Building Modification rather than a simple fit-out.

2. Design by a DHA-prequalified consultant

Only prequalified Health Facility Design Consultants can submit drawings to DHA. They cover medical planning, HVAC, electrical and low-current systems, plumbing with drainage and medical gases, and biomedical engineering. Category 1 consultants design only the smallest facilities, while Category 2 consultants can take on any type. A freelance architect without such a firm cannot make the submission.

Clinic design usually follows Method 1: one detailed design submission and one final inspection. Method 2 (a concept submission covering architecture only, then the detailed design) is mandatory for hospitals. The submission needs an AutoCAD layout showing the area of every room in m² and its labeled function.

3. Initial DHA approval

The DHA facility license is issued in two stages, and the whole DHA approval process for health facilities runs through the Sheryan portal or Invest in Dubai. Paper applications and email are not accepted. The first stage is the New Facility License service. You will need:

  • a trade license, or the proposed trade name and owner details (the license itself is optional at this stage);
  • a facility profile: type, services, specialties;
  • the address with its Makani number, the DM plot certificate (affection plan) and Ejari;
  • the layout from the prequalified consultant with the number of rooms per HFG.

A complete application takes about 5 working days on average. An application left without action for 90 days is cancelled by the system automatically, so DHA comments should be closed out right away. The initial approval fee is AED 500 to 2,000 depending on the facility type (in the DHA catalogue about AED 1,000 for clinics and about AED 2,000 for hospitals and day surgery centers), and Sheryan shows the exact amount. The result is an inactive license valid for 1 year. During that year you cannot see patients or advertise, and if everything is not finished within the year, the process is cancelled and you apply again.

4. Works permits, Civil Defence and DEWA

With DHA approval in hand, get the works permit from the authority for your area:

  • Dubai Municipality. A permit is required for the fit-out of a unit over 100 m². A unit up to 100 m² or one inside a shopping mall needs no permit, but the contractor must still be DM-approved and Civil Defence requirements still apply.
  • DDA. The fit-out permit costs AED 0.90 per sq ft (about AED 9.7 per m²), with a minimum of AED 200 and a maximum of AED 10,000. It takes about 2 working days and is valid for 6 months.
  • DHCC. Design review costs AED 3 per sq ft (about AED 32 per m²), and only DHCA-registered contractors can carry out the works.
  • Trakhees. Modification drawings are approved before work starts, and the unit can be occupied only after the Modification Completion Certificate is issued.

In parallel the drawings go to Civil Defence under the fire safety requirements for UAE construction. Dental rooms, X-ray rooms and day surgery areas need a separate approval for pre-action sprinklers or gas suppression. The electrical load is approved by DEWA. A power connection for a fit-out can only be applied for by a DEWA-registered consultant and contractor. The service itself is free, and the drawings are reviewed in 1 working day.

5. Construction and fit-out

This is the longest stage of medical center construction, and the works schedule is planned around deliveries: medical gas components, special doors and imported sanitaryware are the usual causes of delay. The works are carried out by a licensed contractor, DM-approved on the mainland or DHCA-registered in Healthcare City. Starting before the permit is issued is not allowed and can end in demolition and a repeat site visit. Any construction, renovation or demolition inside a health facility requires an infection control risk assessment: hoarding, negative pressure in the work zone, HEPA vacuums instead of sweeping, and a signed briefing for every worker.

For a fit-out of a clinic that is already operating, the rules depend on the scope. Changing the function of a room means the whole department has to be brought up to the current HFG for the new function. Reworking more than 50% of a department, counting earlier applications, also pulls in the whole department. Below 50%, only the reworked part has to comply. Purely cosmetic work without changes to walls or building services triggers no requirements.

6. Testing and commissioning

Before the inspection the HVAC is balanced per Part E of the DHA Health Facility Guidelines, and you collect the testing and balancing report, a room pressure differential report, an independent medical gas test certificate, the fire alarm commissioning certificate and a DEWA NOC. This is where design supervision of building services and fit-out supervision save the most time and money: the DHA inspector checks the facility only against the approved drawings and does not accept changes made on site.

7. Completion certificates

You need the Civil Defence completion certificate, the DM fit-out completion certificate (if the works required a permit) or the DDA, Trakhees or DHCA equivalent, and FANR registration if X-ray or CT equipment is installed. Radiation shielding is calculated by a FANR-registered specialist, and FANR has to be notified of any new or relocated X-ray unit.

8. Staff, DHA inspection and activation

Activation requires a valid trade license, an appointed medical director, licensed staff, an electronic medical record system connected to NABIDH, and contracts for liability insurance and waste collection. DHA then carries out the final inspection. The outcome is A (approved), B (approved with conditions), C (suspended, a re-inspection is required at AED 500-1,500) or D (rejected). After a successful inspection the Activate Facility License service takes 1 working day on average, and the DHA facility license becomes active.

Medical center requirements in Dubai, room by room

Minimum outpatient room areas under Part B of the DHA Health Facility Guidelines:

RoomMinimum, m²
Consultation and examination room13
ENT or ophthalmology room14
Treatment room14
Procedure room for minor procedures20
Recovery bay after a procedure10 (2 per procedure room)
Clean utility room8-14
Dirty utility room8-12
Accessible toilet6

Add 32% to the room areas for circulation. For example, a unit with 3 rooms takes about 175 m², and one with 8 rooms about 484 m².

What else the inspection checks:

  • patient corridors at least 1,850 mm clear, doors for stretchers and wheelchairs from 900 mm;
  • ceiling height of 2,700 mm, 3,000 mm in procedure rooms;
  • a hand wash basin in every examination room, touch-free taps and wall-mounted soap and towel dispensers;
  • at least 2 waiting seats per room and separate male and female waiting areas;
  • as-built room areas can usually differ from the approved design by no more than 10%;
  • in a two-floor clinic, one treatment or dental room on the ground floor;
  • an accessible toilet on every floor, a lift in a multi-storey building, ramps with handrails.

Finishes are regulated too. Wherever contact with blood and body fluids is possible, floors and walls must be seamless (vinyl, for example), and in wet areas the flooring is coved up the wall by at least 100 mm. Carpet is banned in clinical areas, while tiles with grout joints are acceptable in consultation rooms and corridors. Concealed sliding doors in clinical areas, plants in treatment rooms and curtains outside the permitted cases are not allowed. That is why clinic interior design starts from these limits rather than from a mood board.

Building services in a medical center

The most detailed medical center requirements in Dubai concern engineering. HVAC for clinical rooms is designed to ASHRAE 170, with a Dubai outdoor design condition of 46 °C dry bulb. Each air handling unit has two filter stages, at least MERV 8 and MERV 14. Outdoor air comes in through sand trap louvers, and the building is kept at 5-10% positive pressure.

SystemKey requirement
Examination room and treatment room6 air changes per hour, 2 of them outdoor air, 21-24 °C, humidity up to 60%
Procedure room15 air changes, laminar flow diffusers, fan coil units not allowed
Backup powerexamination room on the generator (start within 15 s), no UPS needed; fuel for an outpatient clinic for at least 4 hours
Lightingexamination room 300 lux, treatment room 500 lux, dental chair 8,000-20,000 lux at the working area
Hot waterstored at 60-65 °C against Legionella, thermostatic mixing valves at basins
Medical gasesto HTM 02-01 or NFPA 99 (one or the other), cylinder manifold room on the ground floor

Supply and return air run only in ducts, and the ceiling void cannot be used as a plenum. If the center has a day surgery operating room or an IVF suite, those rooms follow operating room rules: about 20 air changes, HEPA filters and a dedicated air handling unit for each operating room. For fluoroscopy and interventional procedures the same rules are recommended.

Medical center construction timeline and stages

If the opening is tied to a specific date, plan from the real stages. DHA and DM do not publish an overall official timeline. For a ready unit of 150-250 m² the stages usually look like this:

StageDuration
Survey, layout, coordination with equipment3-6 weeks
DHA layout review with corrections4-8 weeks
Works permit and Civil Defence3-6 weeks, often in parallel
Construction and fit-out8-16 weeks
Testing, inspections, license activation3-6 weeks

That adds up to about 4-7 months, and works in July and August add roughly 2 weeks. Medical center construction in a new building adds site approval, a DM building permit, the structure and the shell, and for a hospital also the two-stage DHA submission, so the timeline is counted in years.

Cost of opening a clinic in Dubai

In the cost of opening a clinic in Dubai, fit-out is the largest item. There are no official rates for it, so below are market ranges for 2026. They include partitions, finishes, built-in joinery, MEP, drainage, fire systems, data networks and permits. They do not include medical equipment, loose furniture, the landlord's shell works or authority fees.

Type of centerAreaFit-out cost per m²
General practice, family medicine120-250 m²AED 2,800-4,500
Dental100-200 m²AED 4,000-7,000
Dermatology and aesthetics150-300 m²AED 4,500-9,000
Day surgery, minor operating room-AED 9,000-15,000 and up

DHA fees are small next to the construction budget: initial approval about AED 500-2,000, final approval about AED 2,000-4,000, and the license fee about AED 5,000 for a general clinic, AED 6,000 for a specialized clinic and up to AED 40,000 for a hospital with more than 100 beds. The fees are non-refundable.

An example. A 200 m² family medicine clinic: fit-out at AED 560,000-900,000, DHA approval and license fees of around AED 8,000, plus equipment and loose furniture. In 2026 construction costs in Dubai are rising by about 4% a year, so an estimate older than six months is worth repricing.

Common mistakes

  • Leasing premises that will not pass DHA. Before signing, check the unit against the medical center requirements in Dubai: space for a medical gas cylinder room on the ground floor if you need gases; a slab height that leaves a 2,700 mm ceiling (3,000 mm in procedure rooms) with ducts above it; routes for the air handling unit and the exhaust riser; spare DEWA capacity; the landlord's consent to medical use.
  • Late decisions on equipment. Equipment is part of the detailed DHA design. Changing models in the middle of the works shifts drainage, power and sometimes walls.
  • Changes on site. The inspector does not approve deviations from the approved drawings, which means a new approval and a paid re-inspection.
  • Conditions that have nothing to do with the works. A finished clinic stays idle without a medical director, doctors' licenses, a NABIDH connection or a waste collection contract.
  • A budget based on general fit-out rates. Such an estimate can be off by a factor of two, because it ignores medical engineering: ventilation, medical gases, backup power.

Frequently asked questions

Can a clinic open in a residential building or villa?

It depends on the zone, and it is the first thing to check when working out how to open a medical clinic in Dubai in a residential area. In most residential zones a clinic is a conditional use: without a separate approval from the DM planning department the premises cannot be used as a clinic, so that approval is obtained before signing the lease and before the design starts. In RC2 a clinic is permitted outright.

How long is the DHA facility license valid?

The inactive license issued after initial approval is valid for 1 year. An active DHA facility license is issued for 1, 2 or 3 years and can be renewed 3 months before it expires.

Can a medical center open before its doctors hold DHA licenses?

Doctors can be licensed under the center's inactive DHA facility license, but their licenses also stay inactive until activation. It is best to submit staff documents right after initial approval: any delay in verifying a doctor's documents moves the opening date directly.

Why does DHA most often send a clinic layout back?

Most often a layout fails DHA approval because of rooms below the minimum clear area, an examination room without a basin or with a manual tap, a sterilization room with no split between clean and dirty zones, or no dirty utility room or medical waste store. Another frequent reason is corridors and doors that drop below the minimum once the real columns and cladding are drawn in. Designs also come back when room names do not match the licensed services, when an X-ray room has no shielding calculation, or when staff and patient routes cross.

What if the clinic has to move to new premises?

Relocating a licensed facility to another building follows the same path as opening a new one: design, DHA approval, works permits, inspection. The DHA fee for changing the facility address is about AED 1,000, and the fit-out of the new premises is budgeted from scratch.

Can work start before the design is approved?

No. First comes DHA approval, then the permit from DM or the free zone authority, and only then the works. Otherwise any deviations have to be redone at the owner's expense.

How is opening a center in Dubai Healthcare City different?

There the license is issued by DHCA, not DHA: a business plan, preliminary approval, fit-out with design review, a pre-operational inspection and the operating license. Works in DHCC are allowed from 18:00 to 6:00 unless DHCA agrees to other hours in writing.

What changes for a dental clinic or a center with X-ray?

A dental clinic needs an instrument processing area of at least 2 m² outside the dental room and 8,000-20,000 lux at the working area, and dental rooms usually get pre-action sprinklers instead of standard wet pipe ones. For X-ray or CT, radiation shielding goes into the design from the start: a FANR-registered specialist calculates it, the shielding thickness comes from that calculation, and FANR registration is obtained before the DHA facility license is activated. Rooms with expensive imaging equipment are protected by gas suppression or pre-action sprinklers. Polyclinics, specialized and dental clinics can offer ultrasound, plain X-ray, CT and MRI, while complex interventional procedures and procedures under sedation or general anesthesia are done only in a hospital.

Bottom line

If you are planning how to open a medical center in Dubai without losing extra months, check the permitted use of the premises before you lease, build the equipment into the design, prepare the design for DHA, DM and Civil Defence at once, and after DHA approval run the works permit, Civil Defence and DEWA in parallel and build strictly to the approved drawings. ZeroMax Group prepares the design, handles approvals and provides design and technical supervision. The DHA submission is made by a DHA-prequalified consultant, and the works in Dubai are carried out by a licensed contractor. To discuss your center, get in touch with us.